E3 Lithium starts Phase 3 at Clearwater demonstration facility

Market News
TSXV:ETL
23 November 2026 03:15 (EST)

Source: Stock image generated with AI.

Key Highlights

E3 Lithium Ltd. (TSXV: ETL) (FSE: OW3) (OTCQX: EEMMF) says it has completed Phase 2 of its Demonstration Facility and has commenced Phase 3 operations for its Clearwater Project east of Olds, Alberta. The company said its direct lithium extraction equipment, commissioned during Phase 1, is now being commissioned at the demonstration facility.

Phase 3 is intended to restart and run E3’s 30-column direct lithium extraction system using brine produced from the Leduc Reservoir at the demonstration site, with the output fed into purification and carbonation equipment to produce battery-grade lithium carbonate.

This article is a journalistic opinion piece which has been written based on independent research. It is intended to inform investors and should not be taken as a recommendation or financial advice.

E3 said Phase 2 included building a full-scale producer and injector well pair to its pre-feasibility study design, and that the wells have produced more than 80,000 m³ of brine to date. The company also reported collecting about 350 samples for brine chemistry and gas content analysis.

As part of Phase 3, E3 also plans to build and operate a larger single direct lithium extraction column to increase processing flow rate and the volume of lithium chloride produced. The company said it is engineering the design and expects to deploy the scaled single column in 2027, with the design decision under final internal review.

Phase 3 targets and engineering timeline

E3 set targets for the 30-column system that include lithium recovery of at least 90%, lithium concentration out of the extraction system of at least 400 mg/L, and lithium carbonate purity described as battery-grade (at least 99.5% Li2CO3).

E3 said Phase 2 commissioning occurred in June 2026 and that Phase 2 operations were extended to adjust the facility and conduct repairs to ensure it continued to operate safely. The company expects front-end engineering design deliverables to continue into 2027 as data is incorporated and engineering ramps up.

Central Process Facility permitting update

E3 said it received notification from the Alberta Energy Regulator that its D056 permit application for the Central Process Facility has entered the second and final phase of the permitting process and is moving to a formal hearing. The company said timelines and details of the process will be provided by the regulator.

The company also said Phase 3 and front-end engineering design are supported by up to $36.5 million in non-repayable funding from Natural Resources Canada’s Global Partnerships Initiative, and that Phase 3 product is intended to support ongoing offtake product qualification.

Read the original press release on Stockhouse.com.