  • Fortuna Silver (TSX:FVI) has announced it is withdrawing production and cost guidance for the year
  • 2020 has not been kind to Fortuna, with COVID-19 shutdowns closing they San Jose Mexico mine, following on-going local protests of the Mexico mine
  • The company’s Lindero Project in Argentina was shut when the Argentinian Government suspended all non-essential activity for a month in March.
  • Fortuna’s silver production is down 19 per cent and gold is down 24 per cent
  • Fortuna Silver (FVI) is trading up 2.9 per cent at C$3.83 per share and has a market cap of $600 million

Fortuna Silver (TSX:FVI) has pulled its production and cost guidance for 2020, after missing its first quarter silver production target by nearly 20 per cent.

The company also announced its production figures for the first quarter of 2020, putting out 1.8 million ounces of silver and 10,101 gold ounces.

That is a 19 per cent decrease in silver production against 2019 figures, and a 24 per cent decrease in gold production.

The company also posted a 5 per cent increase in zinc production to 11 million pounds and an 8 per cent increase in lead production to 7.7 million pounds.

Production expenses have stayed largely flat year on year.

The British Columbia-based Latin American silver miner has two operating silver mines, the San Jose mine in Mexico and the Caylloma mine in Peru.

COVID-19 restrictions have resulted in reduced production at the company’s Peruvian mine and a suspension of operations at the company’s Mexican mine.

The first quarter of 2020 has been not been kind to Fortuna, which has been dealing with local protests at the San Jose mine since before COVID-19 restrictions hit.

The San Jose mine produced 1.5 million ounces of silver and 9,630 ounces of gold for the quarter. This showed an 11 per cent and 16 per cent dip, respectively.

The company put this down to less activity due to COVID-19 and the protests at the site, along with simply mining lower grade mineralisation. The average grade at San Jose for the first quarter was 216 grams per tonne of silver and 1.33 grams per tonne of gold, both reductions year on year.

This was followed by the Argentinan Government shutting down the company’s Lindero project in Argentina.

The site is currently in pre-production and was building towards full production this year.

Prior to the shutdown, Fortuna was producing 40,000 tonnes a day of material at the site, showing that they had indeed the capacity to run the mine at full production.

Fortuna Silver (FVI) is trading up 2.9 per cent at C$3.83 per share at 12:08 pm EST.

More From The Market Online
A gold bar from Dynacor Group's ore processing facility in Peru.

Green flags galore: Why to invest in Dynacor Group today

Gold stock Dynacor Group (TSX:DNG) announces a monthly dividend of C$0.01167 per share for August 2024 with eyes on further growth.
European minerals

Euro Sun Mining completes Critical Raw Materials Act submission

Euro Sun Mining (TSX:ESM) applies to the European Commission for the Rovina Valley Project under the Critical Raw Materials Act.
Drill rig at Corrales target zone on Coppernico Metals' Sombrero project in Peru.

Coppernico Metals begins drilling in Peru with TSX debut in sight

Coppernico Metals begins a drilling program at its Sombrero copper-gold project in Peru, setting the stage for a listing on the TSX.
Gold from Cascadia Minerals' outcrop sampling at its Catch property in the Yukon.

Three Canadian junior mining stocks positioned to thrive

Investors in Canadian junior mining stocks need some of the sturdiest stomachs in the market, but could end up earning multi-bagger returns.