Silver One Resources (TSXV:SVE) completes metallurgical core drilling at Candelaria

Mining
TSXV:SVE
25 August 2022 16:30 (EDT)

Source: Silver One.

Silver One Resources (SVE) has completed a core drilling program for metallurgical testing at its Candelaria project in Nevada.

A total of 1,010 metres in six holes were drilled along the north side of the Mount Diablo pit in an area 300 m long by 200 m wide. The samples collected are being prepared for testing at Kappes, Cassiday & Associates in Reno, Nevada.

Results from the metallurgical testing will be used to evaluate the economics of various processing scenarios, including mixing new mineralization with the historic heap leach mineralization versus processing the heap leach material alone.

Metallurgical core hole coordinates and other identification data (UTM NAD83-11).

DRILL HOLE IDEast (m)North (m)Elevation (m)Azimuth DegDip DegTotal Depth (m)Notes
SO-C-22-13240546342232291851.50-90176.50Sulfide North Diablo pit
SO-C-22-13340549342232341851.50-90193.50Sulfide North Diablo pit
SO-C-22-13440555142232191820.70-90164.60Oxide North Diablo pit
SO-C-22-13540531242230921833.3180-70169.11Oxide North Diablo pit
SO-C-22-13640531442232321857.3180-75145.82Mixed North Diablo pit
SO-C-22-13740538342232471858.7180-80161.21Mixed North Diablo pit
1,010.74
Drill collar and metallurgical bulk samples location map.

Silver One has granted a total of 2,590,000 stock options to its directors, officers, employees, and consultants. The options are exercisable at $0.33 per share for a period of five years from the date of grant.

Silver One is focused on the exploration and development of quality silver projects. The company holds an option to acquire a 100 per cent interest in its flagship project, the past-producing Candelaria Mine located in Nevada. 

Silver One Resources Inc (SVE) is down 1.59 per cent, closing at $0.31 per share.