• Western Resources’ (TSX:WRX) subsidiary, Western Potash, is delaying the completion of its Milestone Phase 1 Project to the end of 2020
  • The Milestone Phase 1 Project is currently 83 per cent finished, and was originally due to be completed in July this year
  • Western Resources cited the impact of COVID-19 and its effect on completing the final tranche of funding for the site
  • The company is working with potential investors and pursuing additional financing options in order to complete the funding
  • Western Resources (WRX) is currently down 20.75 per cent, with shares trading at C$0.21 and a market cap of $38.52 million

Western Resources’ (TSX:WRX) subsidiary, Western Potash, is delaying the completion of its Milestone Phase 1 Project to the end of 2020.

Based in Saskatchewan, the Milestone Phase 1 Project has been designed to test and optimise the company’s horizontal solution mining method, and to investigate how the method can be applied to full-scale potash production.

It’s thought that the site will be the first potash mine to leave no salt tailings at the surface, thereby halving water consumption and significantly improving energy efficiency.

The Milestone Phase 1 Project is currently 83 per cent complete, with the construction of infrastructure, crystallisation ponds, electrical distribution systems, brine heating and pumping systems already finished.

Western Resources cited the impact of COVID-19, which it says has delayed the company’s ability to arrange the final tranche of funding as previously planned. The project was originally due to reach full completion in July this year.

The company is currently engaged in discussion with various potential investors and is pursuing alternative sources of financing for the completion of the remaining construction.

Fritz Venter, President and CEO of Western Potash, stressed that the company is fully committed to completing the project.

“We have already demonstrated that solution mining using horizontal drilling works and completed an impressive amount of the construction of the processing plant.

“Once funding is confirmed we will re-start construction. We have full confidence in the ultimate success of the Phase 1 Project,” he said.

In the meantime, Western Resources said it will continue the operation of full-scale hot mining build up a stockpile of potash in its crystallisation ponds, which will be ready for harvesting by the end of the year.

Western Resources (WRX) is currently down 20.75 per cent, with shares trading for C$0.21 at 3:13pm EDT.

More From The Market Online
Hands holding hard rock spodumene ore, a commercially important source of lithium.

A comprehensive guide to lithium mines in Canada

Learn about key lithium mines in Canada, their role in clean energy and why Canada is becoming a major player in the global lithium…
E3 Lithium logo and landscape

E3 Lithium advances lithium production commercialization

E3 Lithium (TSXV:ETL) reveals it has completed all milestones of the pilot project funded by Natural Resource Canada.
Stock image generated with AI

Buzz on the Bullboards: Stocks to watch as TSX hits new highs

The TSX experienced a roller-coaster of wins and losses this week, yet managed to break a record high with three companies standing out.
Lumps of gold ore from a gold mine

Benton Resources expands gold discoveries in Newfoundland

Benton Resources (TSXV:BEX) reveals results from its South Pond Gold Zone in south-central Newfoundland, leading to significant expansion.