Key Highlights

  • Tusk Automation found no identified conditions preventing a restart of Honey Badger Silver’s PC Silver plant.
  • The board approved Phase 1 to refurbish the crushing circuit, estimated to cost C$1.8 million.
  • Tusk’s schedule targets proof-of-concept testing in late 2027 and concentrate production by mid-2028.

Honey Badger Silver Inc. (TSXV: TUF) has released an engineering assessment that concludes the existing processing plant at its 100%-owned PC Silver Mine in Canada’s Northwest Territories can be refurbished and restarted in phases.

The assessment and phased restart plan were prepared by Tusk Automation Inc. following an on-site inspection of the mine’s processing infrastructure. Tusk concluded the plant can be returned to service and that it did not identify conditions that would prevent a restart.

This article is a journalistic opinion piece which has been written based on independent research. It is intended to inform investors and should not be taken as a recommendation or financial advice.

According to the company, Tusk’s plan outlines three phases that would progressively recommission the crushing, grinding, flotation and concentrate dewatering circuits. The company said the plan is intended to culminate in producing separate lead and zinc concentrates at a rate of 1,000 tonnes per day by the middle of 2028.

Honey Badger Silver’s Board of Directors has approved Phase 1, which would refurbish and recommission the existing crushing circuit, from the ore receiving system through to the fine ore storage bin. Tusk estimated Phase 1 would cost C$1.8 million, and identified the opportunity to complete the work during the 2026-2027 winter season, subject to procurement, mobilization and site readiness.

Phased plan and cost estimates

Tusk estimated Phase 2, which would complete and commission the grinding, bulk flotation and dewatering circuits and enable closed-loop proof-of-concept testing, at C$12.6 million. Tusk’s schedule anticipates commissioning Phase 2 in late 2027, followed by a 28-day pilot testing period extending into January 2028.

Phase 3 would complete remaining flotation, dewatering, power and supporting processing systems needed to produce separate lead and zinc concentrates. Tusk estimated Phase 3 at C$21.2 million and targeted July 2028 for completion of the process plant restart and readiness for full concentrate production at 1,000 tonnes per day, subject to completion and integration of required supporting infrastructure.

The company said the capital estimates include a 15% contingency, with Phase 1 classified as a Class 2 estimate and Phases 2 and 3 as Class 3 estimates. In addition, Tusk identified about C$8.0 million in fuel and air transportation costs associated with the phased restart program, bringing the total indicative program cost to about C$43.7 million.

Honey Badger Silver noted that the estimates relate to refurbishing and completing the existing processing plant and exclude certain supporting infrastructure and development activities, including underground mine development, water treatment, paste backfill, building structural repairs and other facilities required for commercial operations.

Phase 2 and Phase 3 remain subject to further engineering, capital allocation decisions, permitting and the availability of necessary supporting infrastructure and financing, the company said.

Read the original press release on Stockhouse.com.

More From The Market Online

Alphabet faces proposed investor class action over Gemini delays

Kaplan Fox says a class action was filed against Alphabet covering May 19 to July 16, 2026, citing alleged disclosures about Gemini 3.5 Pro…
Legend of Zelda Grand Theft Auto

Bigger than Barbenheimer: The Legend of Zelda vs Grand Theft Auto VI

Grand Theft Auto VI and The Legend of Zelda: Ocarina of Time created a gaming version of the "Barbenheimer" phenomenon, but bigger.
Anthropic Prices Record $81B IPO at $83 a Share

Market Open: Anthropic Prices Record $81B IPO as Nasdaq Rebounds | Nov 19th

Anthropic priced a record $81 billion IPO at $83 as chip stocks rallied, while the TSX fell 2.09% and gold slid below $3,800.

Buzz on the Bullboards: Who knew one man’s affair could ruin the economy?

The stock market has taken a hit in recent sessions as investors grapple with uncertainty surrounding...